Sunday, August 31, 2014

CAPM Question - Managing Changes

The overall process of managing changes that affect the function or characteristics of the deliverable is known as:

A. Managing by exception
B. Change control management
C. Managing by objective
D. Configuration management


Do you know the answer? Leave your comments...

CAPM Question - Change Control Process

The person responsible for ensuring change control is processes through the integrated change control process is the:

A. Project manager
B. Function manager
C. Project sponsor
D. President


Do you know the answer? Leave your comments...

CAPM Question - WBS

This process decomposes the work packages from the WBS into schedule activities:

A. Develop schedule
B. Create WBS
C. Define activities
D. Build activity list


Do you know the answer? Leave your comments...

CAPM Question - Matrix Organization

You are the project manager in a matrix organization and you determine that there are additional human resources needed. From whom would you request the additional resources?

A. The project sponsor
B. The PMO
C. The function manager
D. The team lead


Do you know the answer? Leave your comments...

CAPM Question - Documented Procedures

A collection of formal, documented procedures that defines the steps by which the project may be changed is known as:

A. Managing by exception
B. Change control system
C. Configuration management
D. Managing by objectives


Do you know the answer? Leave your comments...

CAPM Question - Trends

Trend analysis is used to:

A. Improve variance reporting
B. Create change requests
C. Mitigate the harmful effects of scope creep
D. Forecast future project performance


Do you know the answer? Leave your comments...

CAPM Question - Communication Channels

At the onset of your project, you had identified 15 stakeholders. Three more stakeholders have since been identified. How many additional communication channels have been added?

A. 153
B. 120
C. 48
D. 3


Do you know the answer? Leave your comments...

CAPM Question - Estimating

Which of the following techniques is most likely not used in estimating project durations?

A. Parametric
B. Bottom-up
C. Analogous
D. PERT


Do you know the answer? Leave your comments...

CAPM Question - Information Gathering Technique

You have geographically dispersed team members, from whom you would like to anonymously obtain expert opinion on the project you are managing. Which information gathering technique should you use?

A.Brainstorming
B.Delphi technique
C.SWOT analysis
D.Checklists


Do you know the answer? Leave your comments...

CAPM Question - Quality

After quality planning, you have created a component-specific tool to verify that the required steps have been performed to test your product. This can also be referred to as:

A.Checklist
B.Operational definition
C.Quality management plan
D.Design of experiments (DOE)

Do you know the answer? Leave your comments...

CAPM Question - Project Statement of Work

The Project Statement of Work (From buyer perspective) :

A. Is an input to Project Management Integration
B. Occurs during project execution
C. Occurs the end of each project phase
D. Is an output from Project Procurement management

Do you know the answer? Leave your comments...

Monday, August 25, 2014

Welcome to NEWinPM

If you are preparing for the CAPM sooner or later, then you are at the right place in discovering the new approach by NEWinPM in making CAPM study fun and intuitive.

In this blog, you will find the entire content refreshing, assorted and to the latest PMI standards which will help you brush up your concepts once again.

If you need a tool to manage your projects, please go to the link below to review diferent project managements tools.

Herramientas para gestiĆ³n de proyectos


Happy Reading!