Which of the following techniques is most likely not used in estimating project durations?
A. Parametric
B. Bottom-up
C. Analogous
D. PERT
Do you know the answer? Leave your comments...
A. Parametric
B. Bottom-up
C. Analogous
D. PERT
Do you know the answer? Leave your comments...